Data quality and corrections

We publish corrections to our data, including what changed and how many records it touched. Corrections made before a customer saw the data are listed too.

How we classify capacity

Corrections

Entries for September were added to this record on September 27, 2026; later entries carry their own dates.

Con Edison, winter feeder values (September 2026)

What happened: Winter feeder values were not being read from the source field designated for winter capacity.

What changed: We corrected them using the designated field.

Records affected: 857 winter feeder values.

Central Hudson, substation values (September 14, 2026)

What changed: We corrected substation capacity values after removing duplicate feeder records and applying source values in their reported units.

Records affected: 54 substations (108 seasonal values).

Central Hudson, coverage (September 14, 2026)

What happened: Ten substations were no longer present in the source data.

What changed: We retired them. Their historical snapshots remain available.

Records affected: 10 substations.

Orange & Rockland, substation methodology (September 14, 2026)

What changed: We updated substation values to the published normal transformer rating minus observed seasonal peak load. These values suit rapid feasibility screening but do not account for Orange & Rockland's likely N-1 contingency margin. Final interconnection feasibility requires Orange & Rockland confirmation.

Records affected: 555 stored snapshot records are now classified as load-serving headroom. 97 earlier annual rows were replaced by seasonal rows.

United Illuminating, substation values (October 2, 2026)

What happened: Feeder-derived substation values were overstated because historical snapshots from renamed feeders were included.

What changed: Seven values were corrected downward by a combined 79.8799 MW.

Records affected: 7 substation values. Made before customer onboarding.

United Illuminating, coverage (October 2, 2026)

What happened: Stale circuits remained current after source naming changes.

What changed: We retired 31 feeder circuits and 4 substation circuits. Historical snapshots remain available.

Records affected: 35 circuits. Made before customer onboarding.